On the former Fraser Mills site in Coquitlam, BAUER Foundations Canada cleared decades of buried timber piles before installing 132 Cutter Soil Mixing panels to depths of 40.5 m.
BAUER Foundations Canada, the Canadian subsidiary of BAUER Spezialtiefbau, has completed what the company says is the deepest Cutter Soil Mixing (CSM) wall ever built in Canada, on the former Fraser Mills industrial site in Coquitlam, British Columbia. The wall combines shoring and groundwater cut-off for a residential development.
The job shows how much of a deep foundation project on brownfield land is spent dealing with what earlier industries left underground.
From a 115-year sawmill to 5,500 homes
A sawmill operated on the banks of the Fraser River from 1890 until 2005. Developer Beedie Living is now turning the roughly 39 ha site into a waterfront district with around 5,500 homes, commercial space, and public facilities. The Fraser Mills Encore project includes a 32-storey tower with 306 homes, townhomes, and a daycare.
Beedie Living and general contractor B&B Excavating and Shoring Ltd. hired BAUER to pre-drill the alignment and install the CSM wall, which keeps groundwater out of the excavation.
433 pre-drilling holes before the first panel
Pre-drilling turned up boulders, construction debris, and many old timber piles. Instead of relying on isolated test locations, the team pre-drilled systematically along the whole wall alignment: 433 holes to about 12 m deep with a BAUER BG 30 rig and Kelly drilling, using 1,000 mm casing and core barrels, and replaced the material with sand.

The wall itself consists of 132 panels, each 2.8 m long and 640 mm wide, reaching depths of up to 40.5 m. BAUER used a two-phase method: the soil was cut and mixed with bentonite slurry, then grouted as the cutter was withdrawn, with two grout strengths to meet the design. A separation plant processed excavated material and recycled the slurry.
Between May and August 2026, despite early equipment delays and difficult ground, the team installed all 132 panels and 191 steel beams, for about 320 linear metres and 12,291 m2 of wall. The contract was worth CAD 7.4 million.

Next: 185 CFA piles
BAUER’s scope also includes 185 continuous flight auger piles, 610 mm in diameter and up to 28.5 m deep, to support the core of the building. Installation is planned to start in December 2026.
Read the full article here